Castletymon Library
Main Contractor: Construction of New Library Building including all associated services and Re-alignment of the Castletymon Road along the frontage of the new building approx. 60m
- The Project involved the construction of a new Library building of approx. 600m2
- The works included the re-alignment of the main Castletymon Road at a busy junction into the local housing estate.
- MDT carried out all traffic and pedestrian management during the works including diversion of pedestrians and traffic to alternative temporary routes so that works could be completed.
- Strict H&S measures were put in place and a comprehensive traffic management plan put in place by our team. Castletymon Road is a busy two lane road. There is also a local school and children movements during lunch hours had to be carefully monitored.
![company-logo-website](https://b2938279.smushcdn.com/2938279/wp-content/uploads/2022/10/company-logo-website.png?lossy=1&strip=1&webp=1)
OUR CLIENTS
![Department-of-Education-100x100](https://b2938279.smushcdn.com/2938279/wp-content/uploads/2022/10/Department-of-Education-100x100-1.png?lossy=1&strip=1&webp=1)
![DCC-100x100](https://b2938279.smushcdn.com/2938279/wp-content/uploads/2022/10/DCC-100x100-1.png?lossy=1&strip=1&webp=1)
![hse-1-100x100](https://b2938279.smushcdn.com/2938279/wp-content/uploads/2022/10/hse-1-100x100-1.jpg?lossy=1&strip=1&webp=1)
![sligo-hertiage-100x100](https://b2938279.smushcdn.com/2938279/wp-content/uploads/2022/10/sligo-hertiage-100x100-1.png?lossy=1&strip=1&webp=1)
![sligoit-100x100](https://b2938279.smushcdn.com/2938279/wp-content/uploads/2022/10/sligoit-100x100-1.jpg?lossy=1&strip=1&webp=1)
![South-Dublin-CC-100x100](https://b2938279.smushcdn.com/2938279/wp-content/uploads/2022/10/South-Dublin-CC-100x100-1.jpg?lossy=1&strip=1&webp=1)